Work in Live/Occupied Buildings
-

66 Shoe Lane, London
Read moreBrief Description: In the capacity of Principal Contractor, KpH Deconstruction undertook this 15 week Strip Out and Enabling project at 66 Shoe Lane in London, working with Quantum Consulting on behalf of our client, Endurance Land. The site is a vacant 10-storey building, covering 15,000 m².
-

Building 1320, Arlington Business Park
Read moreBrief Description: KpH undertook this 5 week Strip Out and Enabling project for the Client, Patron, as the Principal Contractor, working alongside Beadmans.
-

Crossweys House, Guildford
Read moreBrief Description: KpH Deconstruction undertook this 6 week Strip Out and Enabling project, acting as a Principal Contractor, for our Client, DTZ Investors.
-

Building 1220, Arlington Business Park
Read moreBrief Description: KpH Deconstruction undertook this 6 week Strip Out and Enabling project for the Client, Patron, as the Principal Contractor, working alongside Beadmans.