Work in Live/Occupied Buildings
-
10 Devonshire Square, London
Brief Description: Over a 16 week period, acting in the capacity of Principal Contractor, KpH undertook strip-out and enabling works at 10 Devonshire Square in London working on behalf of our client Blackstones Property Management.
-
Horniman Museum
Brief Description: KpH Deconstruction successfully completed an 10 week Strip-Out and Enabling works project in the South Hall Gallery at the Horniman Museum in London
-
Medicines Gallery, Science Museum
Brief Description: KpH Deconstruction successfully completed an 8 week Strip-Out and Enabling works project in the Medicines Galley (Level 1) at the Science Museum in London.
-
Former BHS Store, St Ann’s Shopping Centre
Brief Description: Acting in the capacity of Principal Contractor, KpH undertook these works at St Ann's Shopping Centre in Harrow over an 11 week period and completed them in April 2017. We managed to improve on the 12 week programme set down by the client whilst also incorporating additional variation works.