Licenced Asbestos Removal
-
Crossweys House, Guildford
Brief Description: KpH Deconstruction undertook this 6 week Strip Out and Enabling project, acting as a Principal Contractor, for our Client, DTZ Investors.
-
1 Leadenhall Street, London
Brief Description: In the capacity of Principal Contractor, KpH Deconstruction undertook this 12 week Strip Out project at 1 Leadenhall Court, Leadenhall Street in London. The project consisted of 11 floors, including a Lower and Upper Basement and a Roof averaging 1800m² per floor.
-
19 – 23 Wells Street, London
Brief Description: KpH Deconstruction undertook this 6 week Strip Out and Enabling project as Principle Contractor at 19-23 Wells Street, London, for the client, British Land, alongside Cost Consultant, Alinea Consulting.
-
Amersham Place, Amersham
Brief Description: We successfully completed a 12 week programme of Strip-Out (back to core) and Enabling works at Amersham Place, an office block consisting of four floors (Lower Ground, Ground, Mezzanine, First and Second), including Roof Top Plant.