Premier House, Edgware
Brief Description: Working to a programme of 16 weeks, the works involved the remaining Strip Out, internal demolition of below window block work, brickwork infills and removal of glazed windows to this 14-storey building.
-
20 Old Bailey
Brief Description: Working as Principal Contractor, KpH undertook this Strip Out and Enabling package across 11 floors together with the removal of Roof Top Plant.
-
Concorde House, Gatwick Airport
Brief Description: Undertaken within a programme of 5 weeks these sensitive works in a busy airport included the strip out of ground to level 3 of Concorde House together with the structural demolition of concrete walls to the interview rooms and cells of this Immigration Handling Unit.
-
Bedfont Lakes
Brief Description: Three-phased major Enabling and Strip Out project spanning 13,000 m² and turning the building back to core. Additional complex dismantling, demolition and enabling works involving the breaking out of concrete slab.