Concrete Demolition

  • O2 Arena, Building 11

    Brief Description: Working alongside the Principle Contractor, ISG, KpH undertook this 7 month Strip Out and Enabling project at the renowned O2 Arena in Greenwich, London,  named “Project Mint”.

    Read more
  • Amersham Place, Amersham

    Brief Description: We successfully completed a 12 week programme of Strip-Out (back to core) and Enabling works at Amersham Place, an office block consisting of four floors (Lower Ground, Ground, Mezzanine, First and Second), including Roof Top Plant.

    Read more
  • 40-41 Great Marlborough Street, London – PHASE 2

    Brief Description: Following a successful enabling works phase, undertaken in the capacity of Principal Contractor, KpH undertook a 13 week demolition programme of a 3 storey extension at the back of 40-41 Great Marlborough Street in London on behalf of GPF Lewis.

    Read more
  • 1 James Street, London

    Brief description: Working as the Principal Contractor for our client, Page Surveyors, KpH Deconstruction completed a 3 x week programme to demolish a detached house, garage and out building at 1 James Lane in London.

    Read more