50 Station Road
Strip Out and Enabling
Client: | Linesight |
Project: | 50 Station Road |
Brief Description:
KpH undertook this 5 week Strip Out and Enabling project working alongside the client’s representative Linesight. The building was split over six floors and our strip out works were across Levels 5, 4, 3 and 2.
KpH put forward a very methodical and careful approach to the strip out works to accommodate the live nature of the offices on Level 1 and Ground Floor. Deliveries/waste removals were carefully coordinated with our waste route being managed around a live communal area shared with the tenants in situ.
As part of our scope of works we were required to retain a number of services, which meant careful consideration and co-ordination with our mechanical and electrical engineers to identify retained services and ensure clear signage displayed for future information. The existing AC units and bathroom ceramics were retained for re-use, as directed by the client.
Scope of Works
Works comprised the strip out and removal of the following:
- floor coverings;
- raised access flooring and conduits skirtings;
- plasterboard and glazed partitions;
- kitchenettes;
- cladding removal of columns to 5th floor and 4th floor;
Images to the left show toilets stripped back to services and items retained as per the client’s instructions