Working as the Principal Contractor alongside Stace, KpH Deconstruction completed a 6 week strip out and enabling contract over three floors (mainly Levels 3 and 4) of a 16 storey building, called Regents Place, at 338 Euston Road in London. We carried out these works for our client British Land.
There were live services running through the floors which fed active offices within the building. KpH therefore had to carefully plan the removal of the redundant M&E services to make sure that there were no unauthorised disruptions for the users of the building. The fire alarm system also had to be retained throughout the works.
The Building Management Team operated a strict Permit to Work system and deliveries and waste skips had to be booked in 48 hours in advance. Waste was removed out of hours in order to facilitate the needs of the building users.
Scope of Works
Strip out works included the removal of the following:
- partitions;
- ceiling tiles;
- floor coverings;
- redundant M&E services;